PROGRESS

Preparation of the site began in December of 2020 which included the demolition of the existing structures as well as the installation of compacted structural stone fill for the building pad. The fill was allowed to settle for a period of eight month with construction of the retaining wall and house commencing in October 2021. The following images represent the progress of the house to date.

PrairieModern%2520logo-pattern-10_edited_edited_edited.png

OCT. 24-31, 2021

Retaining walls, waterline rough-in, septic holding tank installation.

10_24-6.png
10_17-6.png

OCT. 17-23, 2021

Retaining wall footings, job-site toilet, septic tank excavation, waterline rough-in.

OCT. 10-16, 2021

Foundation stake-out, retaining wall footing excavation, silt fencing.

10_10-6.png
11_01-6.png

NOV. 01-06, 2021

Retaining wall drain pipe placed, site security lighting and cameras installed. Concrete footings formed and poured.

NOV. 07-13, 2021

Foundation walls formed, poured and stripped.

11_07-1.png
11_14-2.png

NOV. 14-20, 2021

Stone backfill within foundation walls and around perimeter of regaining wall.

NOV. 21-30, 2021

Final rough backfill of foundation walls and retaining walls.

11_21-3.png
12_02-5.png

DEC. 01-05, 2021

Plumbing and septic rough-in.

DEC. 06-11, 2021

Trusses delivered, rough framing for studio started.

12_06-5.png
IMG_7788.JPG

DEC. 12-31, 2021

Studio framing completed, house framing started.

JAN. 01-15, 2022

Rough framing continues.  Second level sub-floor installed.

IMG_7931.JPG
IMG_8013.JPG

JAN. 16-31, 2022

Rough framing continues.  Second level walls completed.

FEB. 01-12, 2022

Rough framing continues. Upper roof trusses and hold downs installed.  Windows delivered.

IMG_8033.JPG
IMG_8213.JPG

FEB. 13-28, 2022

Rough framing continues. Upper roof sheathing completed, living room framing resumed.

MAR. 01-12, 2022

Major rough framing completed. Start of window installation.  Driveway gravel base installed.

IMG_8270.JPG

APRIL 1-16, 2022

Fascia and soffit installation continues.  Roof installation started.

IMG_8416.JPG
IMG_8363.JPG

MAR. 13-31, 2022

Window installation completed.  Fascia and soffit construction started.

IMG_8454.JPG

APRIL 17-30, 2022

Roof installation continues.  Exterior Trim started. Studio concrete slab poured.

MAY 1-14, 2022

In-floor PEX tubing installed and concrete slab poured on main level.

IMG_8593.JPG
rr-exx.jpg

MAY 15-31, 2022

Garage in-floor Pex tubing placed and concrete slab poured.  Temporary stairs installed.

JUNE 01-15, 2022

In-floor PEX tubing installed and gypcrete poured on second level. Start of exterior stonework. 

Skylights installed.

IMG_8766.JPG
IMG_8849.JPG

JUNE 16-30, 2022

Exterior masonry work continues.  Concrete auto-court and walks poured. Mechanical Rough-in.

JULY 01-15, 2022

Exterior Stucco installation started.  Concrete auto-court poured. Interior masonry fireplace installedGlass garage doors installed.

IMG_8946.JPG
IMG_9034.JPG

JULY 16-31, 2022

Exterior masonry work completed.  Exterior stucco installation completed.

AUGUST 01-15, 2022

  Electrical rough-in started.

IMG_9127.JPG
IMG_9225.JPG

AUGUST 16-31, 2022

Rough-in inspection. Terrace grading.  Insulation installation.